The term “general conditions” in construction cost parlance describes expenses that support a project without directly relating to job site activities like pouring concrete or mounting steel beams. They are the indirect costs of construction, carried at the job site, and they are not the same thing as soft costs, which are the non-construction costs of a project: design fees, legal work, financing and the like.
Table of Contents
The associated infrastructure and equipment do not get handed over to the client along with other components (including the structure itself) following the project’s completion.
Keep reading to learn more about general conditions construction costs, including where they fit into the project planning process.
What is General Conditions in Construction?
General conditions are the indirect costs of a construction job site: supervision, the job trailer, temporary utilities, fencing, security, cleanup, permits, insurance and bonds. They are the cost items Division 01 of the specifications calls for: construction cost, not soft cost. On typical commercial work they run 6-12% of total job cost (Construction Executive, 2018); across all project types the National Park Service puts the range at 4-20% of construction cost, depending on size, location and complexity (2007). Where a funding program caps them, the cap lands near 6% of hard construction cost, as HUD’s mixed-finance standard (2003) and Connecticut’s 2026 housing guidelines do. Those are caps, not averages, and every figure here is a share of construction cost, not of total project cost with land, design and financing included.
In construction, General Conditions represents a set of terms, services, and expenses crucial to running a project smoothly—without directly tying into physical construction tasks like pouring concrete or installing fixtures. These costs are like the operational backbone, covering the administrative, logistical, and legal aspects that allow the hands-on work to proceed effectively. General Conditions define the project’s working framework, laying out management duties, roles, and all the support costs necessary for the project’s successful completion.
At its core, the purpose of General Conditions is to create a solid structure for project execution. This framework clarifies stakeholder responsibilities, establishes decision-making pathways, and specifies indirect costs that underpin the construction work. This structure also helps reduce risks and maintain project continuity, all while enforcing essential guidelines and standards. By addressing these elements, General Conditions help ensure that the project is well-organized, financially sound, and completed on time.
Key Component of General Conditions: All indirect costs critical to project management and operational stability, enabling efficient coordination of construction activities.
| Key Component | Description |
| Project Administration | Defines roles and responsibilities, decision-making processes, communication channels, and the chain of command for project execution. |
| Project Schedule | Outlines start and completion dates, milestone deadlines, and potential penalties or incentives related to the schedule. |
| Payment Terms | Includes payment schedules, invoicing procedures, and retainage terms necessary for project cash flow management. |
| Site Management | Covers temporary facilities (trailers, offices), security measures, safety protocols, and waste removal services essential for site operations. |
| Project Management | Encompasses supervision costs, expenses for project managers and field office staff, and other overhead costs related to onsite management. |
| Material Handling | Accounts for equipment rentals and labor costs involved in material delivery, protection, and staging on the job site. |
| Calculation Methods | General Conditions are typically calculated as either a percentage of the construction cost or a lump sum included in the project bid for operational expenses. |
Examples of general conditions construction costs
AIA Contract Documents sources these eight general conditions categories to Article 7 of the A102-2017 cost-plus agreement (updated March 2026):
| General conditions category | Typical line items |
| Project administration | Wages, salaries and benefits for superintendents, project managers and site admin staff |
| Temporary facilities | Job trailers and site offices, portable restrooms, storage units |
| Cleanup and waste management | Debris removal, construction waste disposal |
| Permits, inspections and testing | Permit fees, required inspections, materials testing |
| Safety and security | Safety equipment and training, security personnel or surveillance |
| Mobilization and demobilization | Getting people, equipment and facilities on site and off again |
| Weather protection | Temporary enclosures, weatherproofing |
| Insurance and bonding | General liability insurance, performance bonds |
Construction Executive splits these into fixed and variable general conditions costs: signage and mobilization do not change with duration, while trailer rental grows with every week added to the schedule (2018). That split is why the schedule drives the estimate.
Here are a few expenses commonly placed in the general conditions category. This is not an exhaustive list, mind you. The general conditions category can include many hundreds of expenses. However, this list should give you an idea of what constitutes general conditions.
Pre-development fees
Construction companies typically put lots of effort into a given project before even receiving the contract. For example, staff prepares estimates and bids, both of which take considerable time.
Naturally, there are costs associated with these activities. The most obvious of these would be the staff’s salaries.
Strictly, though, this is company overhead rather than a project’s general conditions. The work happens before there is a contract to charge it to, and none of the standard enumerations, AIA’s A102 Article 7 categories among them, include it. Some contractors track it here anyway.
Administrative project costs
Of course, administrative tasks don’t end once the project begins. Away from the job site, staff members carry on with tasks such as payroll and addressing human resource concerns.
Without this work, the project would grind to a halt. However, because these costs are not directly related to manual labor on the job site, they’re classified as general conditions.
Project equipment and utilities
This category contains expenses such as dumpsters, fencing, temporary lighting, and site office utilities.
These costs differ from things like bulldozers and jackhammers, both of which might be absolutely essential for project delivery. The aforementioned general conditions, however, support the entire project in a more indirect sense.
Permits
If a project requires permits, these will also typically be lumped in with general conditions. Permit fees include any costs (including staff member salaries) incurred during the process of receiving the legal authorization required for work to commence.
Loan interest
When a contractor borrows specifically to carry a project, some firms put the interest under general conditions. Conventionally, though, financing cost is the owner’s soft cost, or the contractor’s company overhead, and it appears in none of the standard enumerations of general conditions, from AIA’s A102 categories to the Massachusetts DCAMM estimating checklist.
Taxes
Many taxable events typically occur during large-scale construction projects. These taxes – and any fees associated with handling them (i.e. accountant wages) fall under general conditions.
Project management
Construction project management is a term broadly describing a whole laundry list of activities that support work on the job site. It covers areas such as:
- financial
- time
- quality
- contract
- safety
- workforce
Each of these costs falls under the category of general conditions.
Public relations
Public-facing construction companies often incur costs associated with maintaining their reputations and other advertising-related concerns. Those are company-wide costs, so by the overhead test further down this page they are general overhead, not general conditions, and no standard enumeration lists them. The exception is project-specific work the job calls for, such as job signs, progress photographs or a project webpage, which Construction Executive does list among general conditions (2018).
Worker accommodations, amenities, and additional compensation
Often, construction projects require workers to relocate or even just travel long distances to the job site. This category covers expenses related to that travel, including hotel bookings, compensation for gas, and air travel.
Job site setup and cleaning costs
Costs in this category cover the initial setup of a construction project along with the cleanup that happens once everything’s complete. These costs fall under general conditions.
How are top contractors handling the labor shortage?
Bridgit surveyed 250 construction leaders at $100M+ firms. 80% already use AI in workforce planning. See what the rest of the industry is doing.
Why general conditions construction costs matter
General conditions can heavily influence a project’s financials. In fact, profitability may hinge on a company’s ability to create accurate general conditions construction cost estimates and incorporate those figures into their planning.
Take another look at the examples in the previous section. These aren’t necessarily minor costs, especially on larger construction projects. When companies don’t account for them, they may end up with a completely inaccurate understanding of their profit margins.
This can have devastating implications down the line. Say, for example, a construction company thinks they have a $5 million surplus on a particular project, unaware that $2 million of that figure is actually being eaten up by improperly-tracked general conditions.
The company could conceivably overextend itself by allocated those resources – which it doesn’t actually have – elsewhere.
Whether the owner ever sees that number, and who carries it when it is wrong, depends on the delivery method. Under lump sum on AIA A201 terms, general conditions are folded into the contract sum and the contractor carries the estimate. Under cost-plus with a GMP they are a reimbursed cost of the work, tracked line by line and supported to the owner; AIA A102 Article 7 and ConsensusDocs 500 Article 8.2 list the items. A common hybrid is a negotiated lump sum for general conditions plus an agreed percentage or daily rate on change orders for time (Construction Executive, 2018). Under Washington State’s public GC/CM model they sit outside the maximum allowable construction cost, bid or negotiated as specified general conditions, either a monthly not-to-exceed amount or a percentage of construction cost, per the state’s GC/CM best-practice chapter, which is guidance, published as a draft in March 2023.
Under lump sum a bad estimate comes out of your margin. Under cost-plus it is a line the owner audits.
How to Estimate General Conditions?
Estimating general conditions for a construction project starts with reviewing historical data from past projects of similar size, type, and duration. This provides a helpful baseline for what general conditions might cost. Next, break down general conditions into specific items, including costs for project management, temporary site facilities like offices or storage, safety measures, utilities, equipment rentals, permits, inspections, and site security. With this breakdown, estimate the project’s duration, as many general conditions costs depend on the length of time they’re needed.
Once the list is established, calculate the costs for each item based on either time or quantity. For instance, multiply the rate of time-dependent items (such as salaries) by the project’s estimated duration, while quantity-based items (like dumpsters) should be estimated by quantity needed, then multiplied by unit costs. To ensure your estimate remains accurate despite potential price fluctuations, consider using futures contracts for larger projects or materials tracking software that provides current price forecasts.
It’s also wise to include a contingency to cover any unexpected expenses. Add up all these costs to arrive at a total estimate for general conditions. Depending on the contract, you may express this estimate as either a lump sum or a percentage of the construction cost. Lastly, be prepared to justify the costs you’ve included, avoiding items such as staff bonuses or depreciation, which clients may not be willing to cover. Using construction estimating software can streamline this process, and by maintaining detailed records of actual general conditions costs from completed projects, you’ll improve the accuracy of future estimates.
One thing to be clear about: the percentage is the check, not the method. General conditions are built up from staffing and duration, a weekly or monthly rate for the superintendent, trailer, utilities and toilets carried across the schedule, plus one-time items like mobilization and signage. The National Park Service’s estimating handbook allows a percentage of direct cost at the summary stage of an early estimate, but requires general conditions broken out in detail at MasterFormat level for a Class A, or final, estimate (2007). If your line-by-line buildup lands well outside 4-20% of construction cost, something in the duration or the staffing plan is wrong.
Difference between general conditions and general overhead
It’s worth noting that general conditions differ substantially from general overhead.
You see, general conditions are attached to a specific project. General overhead, meanwhile, consists of expenses a company incurs as part of simply staying open (i.e. leasing office space and paying administrative staff, neither of which are attached to a specific job).
Here’s another way to think of it. General conditions are crucial for determining whether a project will be successful. General overhead, meanwhile, can help a company determine whether its entire operation is successful.
General conditions vs general requirements in construction
General conditions are the contract’s terms. General requirements are the specification sections that administer those terms on a specific job. And “general conditions” is also what contractors call the jobsite indirect costs of meeting both, which is why the two terms get used interchangeably.
In CSI MasterFormat 2018, General Conditions are 00 72 00 in Division 00, Procurement and Contracting Requirements: the rights, responsibilities and relationships of owner, contractor and architect, adopted by reference into every agreement on the job. AIA A201-2017 is the standard form, written by a standard-form publisher or the owner’s lawyer, not per project. General Requirements are Division 01, nine sections from 01 10 00 Summary to 01 90 00 Life Cycle Activities, written by the specifier for each project: submittals, scheduling, quality, temporary facilities and controls, closeout. The cost category belongs to the contractor’s estimator, built from duration and staffing: supervision, temporary facilities, security, cleanup, permits, bonds.
The overlap is real. The National Park Service defines a contractor’s general conditions as “basically the cost items defined in the Division 1 specifications” (2007), and Connecticut’s 2026 housing guidelines cap “general requirements, also known as general conditions” at 6% of total hard costs. Which term is right depends on whether you are holding a contract, a spec book or a bid.
Tips for general conditions construction cost estimates
Next, let’s discuss some tips and best practices for ensuring your general conditions construction cost estimates are accurate.
Rely on data from past projects
Because general conditions can vary based on a project’s type, it’s crucial that you maintain reference points. You should be able to reference this data whenever you prepare general conditions construction cost estimates for similar projects in the future.
Of course, this all begins with appropriate tracking. From a resource management perspective, consider using software like our very own Bridgit. This software will help you visualize resource allocations, which you can then use to determine how much capital is being allocated to specific tasks, including those that fall under the purview of general conditions.
Bridgit also includes a forecasting feature that can help you project future needs, which you’ll find valuable for general conditions estimating.
Supervision is the general conditions line that is set by who you assign and for how long, and it moves with every week the schedule moves. Tracking that across past projects of similar size and duration is the same data that makes workforce planning for general contractors predictable rather than reactive.
Do your best to forecast fluctuations in pricing for materials and equipment
Here’s a general conditions estimate example.
Let’s say you’re looking to estimate the cost of job site fencing, which certainly falls into the category of general conditions. Months down the road, though, it’s possible the price of fencing may rise.
On large scale construction projects, companies may use futures contracts to secure very specific prices for materials and equipment. In other words, these contracts hedge against the possibility of those costs exceeding the strike price.
On smaller projects, companies may simply rely on building materials software that keeps track of prices across numerous vendors.
Whichever approach best meets your needs, it’s important you make an effort to forecast costs for items related to general conditions.
Be prepared to justify your general conditions
As you’ve probably noticed by now, the general conditions category contains relatively vague line items. As such, contractors are often asked to justify these expenses before a proposal is approved or reimbursement is issued.
You’ll have a much easier time getting your general conditions approved by:
- avoiding the inclusion of staff bonuses and other incentives; clients typically don’t want to pay for this
- being selective regarding listing equipment depreciation as a general condition; some clients may insist this constitutes general overhead
- ensuring the general conditions rates you quote are in line with market averages, even if you have alternative arrangements with suppliers
- maintaining records (including receipts) of transactions and passing those along with your requests for reimbursement
We hope this guide has helped you better understand the idea of general conditions as they relate to construction costs.
For more construction management explainers and tips, visit our blog.
General Conditions FAQ
What are general conditions vs general requirements in construction?
General conditions are the contract’s terms, filed at MasterFormat 00 72 00, with AIA A201 as the standard form. General requirements are the Division 01 specification sections that administer those terms on a specific job: submittals, scheduling, quality, temporary facilities, closeout. Contractors also call the jobsite indirect costs of meeting both “general conditions”, which is where the two get mixed up.
How do general conditions affect the overall project budget?
General conditions make up a significant share of construction cost: about 6-12% of total job cost on typical commercial work (Construction Executive, 2018), and 4-20% across all project types (National Park Service, 2007). Because they are indirect, they are the easiest costs to under-track, and on cost-plus contracts the owner will ask for documentation to validate them throughout the project.
What percentage of total project costs should general conditions represent?
Measured against construction cost, not total project cost: about 6-12% on typical commercial work, and 4-20% across all project types depending on size, location and complexity. Funding programs that set a ceiling, such as HUD’s mixed-finance standard (2003) and Connecticut’s 2026 housing guidelines, cap it at 6% of hard construction cost. Those are caps, not averages.
How can general conditions be adjusted for different project phases?
Adjusting general conditions by project phase involves evaluating needs such as site supervision, rented equipment, and temporary facilities, then calculating costs accordingly. Each phase should reflect its unique requirements and projected duration.
What documentation is required to substantiate general conditions for client approvals or audits?
To verify general conditions, it’s helpful to have records such as timesheets, invoices, permits, and inspection reports. These documents ensure transparency and justify the costs that are indirectly tied to the project.